Grid connection is the bottleneck. We work on it.

Germany has around 3 GW of data centre capacity, and the federal government wants to double it by 2030. In the metros, grid connection is the obstacle: Frankfurt is not granting large new connections until the mid-2030s, Berlin and Hamburg are rationing. In the north, the power comes ashore. That is where we develop.

100 MW
Secured, redundant starting capacity that operators demand; path to 300 to 500 MW.
2028 to 2030
Energisation the market demands; 2031 already counts as late.
1,000 m2
Land per MW that we assume in site screening.
100 to 200 h
Curtailment per year that operators accept in flexible connection agreements.

What a GDI site includes at handover

  • Documented 380 kV connection path with a staged plan

    First stage 100 to 250 MW, expansion to 500 MW and more.

  • Contiguous land under contract

    Around 1,000 to 1,250 m2 per MW.

  • Formal zoning resolution or statute for a Sondergebiet Rechenzentrum

    Special-use zoning for data centers.

  • Energy concept

    Generation, storage, flexibility offer, backup power.

  • Heat concept with offtakers or a documented exemption

  • Operator shortlist and handover package for the data room

The stages to handover

1

Screening

Screening and preliminary check with the grid operator.

2

Land

Land options and formal zoning resolution.

3

Maturity procedure

Application in the Reifegradverfahren (maturity procedure) with connection concept, proof of financing and flexibility offer.

4

Energy and heat

Energy and heat concept.

5

Operator selection

Operator selection and data room under NDA.

6

Handover

Handover.

1

Screening

Screening and preliminary check with the grid operator.

2

Land

Land options and formal zoning resolution.

3

Maturity procedure

Application in the Reifegradverfahren (maturity procedure) with connection concept, proof of financing and flexibility offer.

4

Energy and heat

Energy and heat concept.

5

Operator selection

Operator selection and data room under NDA.

6

Handover

Handover.

How we work with operators

We hand sites to the operator that brings them online fastest. We work with hyperscalers, developers, infrastructure funds and German anchor users, and we can organise several operators at one node. For users who only take turnkey, we bring a build-to-suit partner. You receive documentation after signing a non-disclosure agreement.