We develop the pre-stage. The operator builds.

A large data centre in Germany rarely fails on capital and rarely on land. It fails on grid connection, on building rights and on time. GDI takes on exactly this pre-stage.

The process in seven steps

1

Screening

We check transmission nodes, power plant sites and offshore landing points for available or soon-available connection capacity, land and surroundings.

2

Land security

We secure contiguous land via options, not purchases. Owners remain owners until an operator is confirmed.

3

Zoning

With municipality and district we run the process for a Sondergebiet Rechenzentrum (special-use zoning for data centres), including the environmental assessment.

4

Grid connection

We file the application in the transmission system operators' Reifegradverfahren (maturity procedure): land security and permitting status, technical connection concept, capability of the applicant, grid and system benefit.

5

Energy and heat

We structure direct supply from wind and solar, storage at the connection point, flexibility towards the grid and waste heat use under the EnEfG (Energy Efficiency Act).

6

Operator selection

We select the operator together with the municipality: hyperscaler, developer or German anchor user, depending on the site.

7

Handover

The operator takes over land, building rights, connection path and concepts, and builds.

1

Screening

We check transmission nodes, power plant sites and offshore landing points for available or soon-available connection capacity, land and surroundings.

2

Land security

We secure contiguous land via options, not purchases. Owners remain owners until an operator is confirmed.

3

Zoning

With municipality and district we run the process for a Sondergebiet Rechenzentrum (special-use zoning for data centres), including the environmental assessment.

4

Grid connection

We file the application in the transmission system operators' Reifegradverfahren (maturity procedure): land security and permitting status, technical connection concept, capability of the applicant, grid and system benefit.

5

Energy and heat

We structure direct supply from wind and solar, storage at the connection point, flexibility towards the grid and waste heat use under the EnEfG (Energy Efficiency Act).

6

Operator selection

We select the operator together with the municipality: hyperscaler, developer or German anchor user, depending on the site.

7

Handover

The operator takes over land, building rights, connection path and concepts, and builds.

What a GDI site includes at handover

  • Documented 380 kV connection path with a staged plan

    First stage 100 to 250 MW, expansion to 500 MW and more.

  • Contiguous land under contract

    Around 1,000 to 1,250 m2 per MW.

  • Formal zoning resolution or statute for a Sondergebiet Rechenzentrum

    Special-use zoning for data centers.

  • Energy concept

    Generation, storage, flexibility offer, backup power.

  • Heat concept with offtakers or a documented exemption

  • Operator shortlist and handover package for the data room

What we ask of partners

  • The state

    Designate focus regions at transmission nodes, appoint a coordinator for large-load settlements, speed up permitting.

  • Municipality and district

    A clear position, access to owners, the formal zoning resolution as soon as the grid operator has classified the capacity.

  • Grid operators

    A structured dialogue inside the procedure. We work within the Reifegradverfahren, not around it.